If unchecked the project will actually cost $ 56,380 and it will be finished in 32 days or until 06/16/05. BAC = $65,000 BCWP = $48,750 = .75 * 65000 (percentage completed * Baseline Cost) ACWP = $42,250 = .65 * 65000 (effort spent * Baseline Cost) CPI = 1.15 = 48750/42250 = (BCWP/ACWP) EAC= $56,380 = ((BAC-BCWP)/CPI) + ACWP = 65000-48750/1.15 + 42250 = 16250/1.15+42250 = 14130 + 42250 SV= $-16,250 = EV (BCWP) - PV (BCWS) BCWS (Current Date - Baseline Start Date) x Baseline Cost / Baseline Duration. (05/15/05 – 03/02/05) x 65,000 * (/ 02/03/05 to 26/04/05) 74 *65,000 / 55 = 87454.55 SPI = BCWP / BCWS SPI=48,750/87454.55 SPI = .56 or SPI = 1.44 ISAC = /SPI 03/02/2005 -> 05/15/2005 = 74 days 74d * SPI = ISAC 74d * 1.44 = 106days ISAC = in 32 days or on 06/16/05 eac is my estimate at completion